Friday, 18 June 2010

Fun and games with the East Coast franchises

Just before Christmas, I attended an ASLEF meeting in Newcastle where one of the main topics was the proposed cutting of direct services between Kings Cross - Glasgow Central via Motherwell. This isn't a particularly radical suggestion as it's an hour or so slower getting this service than walking 10 minutes down the Euston Road and getting the Virgin service. It also doesn't mean a reduction in services between York and Glasgow because the idea is to transfer existing paths over to Cross Country.
Other than the odd traveller from Peterborough, Grantham or Newark, these proposals will mainly impact the staff who operate them. There are bound to be alterations to the compliments of drivers needed at relevant depots and I imagine, unless TUPE employment legislation kicks in, there will be some redundancies amongst catering and cleaning staff.

There was clearly some momentum behind these changes, with documents being issued from DfT, East Coast and ORR and Cross Country even started to recruit new staff in Edinburgh, Newcastle and Leeds. Since the election purdah kicked in, its all gone very quiet though and I'll suspect that the Franchise Review announced by the new coalition government has messed everything up. Don't forget it takes a year to get a new driver out working and it takes much longer than that to plan a new railway timetable this big because there are so many stakeholders and resource changes required.
In the mean time, no one has a clue what's going to happen apart from furtive whispers from the odd geordie guard claiming its DEFINITELY going to happen. However, with this new regime, all bets are off.

Sunday, 31 January 2010

Just a few thoughts about how green trains can be:

A train can hold more than 100 people per carriage. In the rush hour, my train is usually 8 carriages long. Realistically, I'm carrying about 500 prevented car journeys per commuter trip. It's even better than this because as long as the signals stay green and friendly, I regularly coast all the way from Brixton to Victoria - that's about 7 miles without troubling the National Grid.


Saturday, 9 January 2010

Why the cold affects the trains

So your train was cancelled this week... here's some of the real technical reasons why the trains I was driving stopped running.

First off, the trains in South East England that I drive use an electric system called 750 v DC third rail. There is a third rail that carries the power and a collector shoe contacts with this rail to provide the train with power. It was first used in the 1920s and is a lot cheaper to install than other more modern systems. The problem is that it can ice up. When Ice gets onto this rail it pushes the shoe away from the rail and stops any power getting to the train. Even if the current reaches the train it is not "clean" power, with huge voltage spikes. Now everyone should remember their physics at school which says I = R/V. If you have a change in resistance then it'll affect volts and amps. On old trains, the technolgy was basic and like something from a frankenstein movie. the thing would keep arcing and sparking, but keep juddering along. With modern trains that have electronics, the safety systems simply take one look at the power supply and decide to shut the train down to save it from catching fire. That's progress for you.

Of course, we've been experiencing other major problems too. First off, brakes have started freezing up, which is a bad thing. We even had one kind of train that has sliding doors and ice has frozen them all together.

OK, so technical problems aside and given staff have mostly been getting to work, what else has gone wrong? Well, as i menioned in my last blog entry. When trains are in the wrong place, there's a lot of work and resource needed to get it to the right place, also when one train fails, the system becomes congested with trains backing up behind that failed one. Remember what I said about the conductor rail ice? Well it becomes a real issue if you stop a working train on it.. that train often then fails... hence more trouble.

Today's train operators are so worried that they predict train armageddon and bring in an emergency shoestring timetable.. one an hour etc.. even when this is an overreaction. The entire thing becomes a vicious circle. Not enough trains keeping the rails clear, meaning that trains that venture out then fail.

The main electric line from Kings Cross to Doncaster was mostly paralysed yesterday, wheras the diesel St Pancras - Sheffield line was working on time and to a normal weekday timetable.